The short version
- Two separate permissions. Planning is the council's. Telling the environmental regulator before you build is a different, separate duty — see storage rules by nation.
- Permitted development can cover a lot of farm work — but only if every condition in the law is met. If one fails, you need a full planning application.
- The 400 m rule (England, Wales, Scotland). No permitted development for a slurry store "within 400 metres of the curtilage of a protected building" — broadly, a house or other occupied building that isn't part of a farm.
- Prior approval (England, Wales, Scotland). For a new building and some other works, you ask the council first whether it wants to approve the siting and design. It has 28 days to say.
- Northern Ireland works differently. No 400 m slurry rule, but a store can't go within 75 m of a non-farm house, must be within 75 m of the main farm buildings, can't be the first building on the unit, and has a 500 m² limit.
- Size and place limits apply everywhere — ground area, height, distance from roads and minimum farm size. They differ by nation.
- Ask the council before you commit. Whether a project is permitted development is a legal question and the council decides it. This page helps you ask the right questions.
Side by side
Agricultural permitted development as it applies to a slurry store. Figures are from each nation's planning order; the detail and exact wording are in the nation sections below.
| England | Wales | Scotland | Northern Ireland | |
|---|---|---|---|---|
| Planning order | General Permitted Development (England) Order 2015, Sch. 2 Part 6 | General Permitted Development Order 1995, Sch. 2 Part 6 (as it applies in Wales) | General Permitted Development (Scotland) Order 1992, Sch. 1 Part 6, Class 18 | Planning (General Permitted Development) Order (NI) 2015, Schedule Part 7 |
| Minimum farm size | 5 ha for new buildings and works (Class A); 0.4–5 ha: extensions and alterations only (Class B) | 5 ha for new buildings and works (Class A); 0.4–5 ha: extensions and alterations only (Class B) | Not on agricultural land less than 0.4 ha | Not on agricultural land less than 0.5 ha |
| Slurry store near houses | Not within 400 m of the curtilage of a protected building | Not within 400 m of the curtilage of a protected building | Not within 400 m of the curtilage of a protected building | No building or structure less than 75 m from a dwellinghouse (other than one of someone farming the unit) |
| Ask the council first | Prior approval application; 28 days | Prior approval application; 28 days | Prior approval application for buildings and private ways; 28 days | No prior approval step in Part 7 |
| Ground area limit | 1,000 m² (works or structure for livestock, or plant or machinery from engineering operations); 1,500 m² (buildings) | 465 m² | 465 m² (works or structures); buildings 465 m² in a designated area, 1,000 m² elsewhere | 500 m² |
| Height limit | 12 m — or 3 m within 3 km of the perimeter of an aerodrome (airport in Northern Ireland) — in all four nations | |||
| Near roads | Not within 25 m of the metalled part of a trunk or classified road | Not within 25 m of the metalled part of a trunk or classified road | Not within 25 m of the metalled portion of a trunk or classified road | Not within 24 m of a special road, or of the middle of a trunk, first- or second-class road; 9 m from the middle of other roads |
| Other NI conditions | — | Not the first agricultural building on the unit; within 75 m of the nearest part of a group of principal farm buildings | ||
The 400 m rule
What it says
England's order says permitted development does not cover anything that "would consist of, or include, the erection or construction of, or the carrying out of any works to, a building, structure or an excavation used or to be used for the accommodation of livestock or for the storage of slurry or sewage sludge where the building, structure or excavation is, or would be, within 400 metres of the curtilage of a protected building". Wales has the same wording. Scotland's version covers buildings, structures or erections used for "housing pigs, poultry, rabbits or animals bred for their skin or fur or for the storage of slurry or sewage sludge".
There is a matching condition the other way round: anything built under these rights within 400 m of a protected building must not then be used for storing slurry or sewage sludge.
What counts as a "protected building"
England: "any permanent building which is normally occupied by people or would be so occupied, if it were in use for purposes for which it is designed; but does not include— (a) a building within the agricultural unit; or (b) a dwelling or other building on another agricultural unit which is used for or in connection with agriculture". Wales and Scotland define it in almost the same words.
So your own house and buildings on your unit don't count, and nor does a farmhouse or farm building on another farm that is used for agriculture. A non-farm house, a business unit or a school within 400 m generally would.
Note the order measures to the curtilage of the protected building, not to the building itself.
Inside 400 m?
Permitted development does not cover it, so you would need to apply for full planning permission. That is not a refusal — it means the council looks at the proposal in full.
Prior approval: asking the council first
How it works
Before you start, you "apply to the local planning authority for a determination as to whether the prior approval of the authority will be required" (England's wording). The application includes "a written description of the proposed development and of the materials to be used and a plan indicating the site together with any fee required to be paid".
You may not start until one of these happens: the council tells you in writing that prior approval is not required; the council tells you within 28 days that it is required, and then gives it; or 28 days pass without the council deciding or telling you.
The work must then follow what was approved (or what you submitted), unless the council agrees otherwise in writing, and must be carried out within 5 years.
What it applies to
England and Wales: "the erection, extension or alteration of a building", "the formation or alteration of a private way", "the carrying out of excavations or the deposit of waste material (where the relevant area … exceeds 0.5 hectares)", and placing a tank in any waters. For extending or altering a building, only a "significant" extension or alteration needs it, unless the building is on certain designated land. The council looks at siting, design and external appearance (for an excavation, its siting).
Scotland: the erection of a building, or its significant extension or alteration, and forming or altering a private way.
Whether a particular tank, bag or lagoon is treated as a "building", a "structure" or an "excavation or engineering operation" affects which conditions apply. The orders don't list store types, so ask the council how it will treat yours.
Site notice
If the council says prior approval is required, you must put up a site notice "on or near the land" and leave it up for "not less than 21 days in the period of 28 days" from the council's notice.
England
Class A: farms of 5 hectares or more
Covers "works for the erection, extension or alteration of a building" and "any excavation or engineering operations, which are reasonably necessary for the purposes of agriculture within that unit". Not on a separate parcel of the unit under 1 hectare.
Limits relevant to a store: ground area of "any works or structure (other than a fence) for accommodating livestock or any plant or machinery arising from engineering operations" no more than 1,000 m²; any building no more than 1,500 m² (both limits set in May 2024); height 12 m (3 m within 3 km of an aerodrome); not within 25 m of a trunk or classified road; the 400 m rule; not on, or within the curtilage of, a scheduled monument (for erecting or extending a building).
Class B: farms of 0.4 to 5 hectares
Extensions and alterations of an existing agricultural building, plant and machinery, hard surfaces and similar — not a new building. Works to a slurry store "within 400 metres of the curtilage of a protected building" are not covered. An extension can add no more than 25% to the original building's cubic content, must not raise its height, and must not be within 5 m of the unit boundary.
Environmental impact assessment
Development that falls under Schedule 1 or Schedule 2 of the EIA Regulations 2017 is not permitted development unless it has been screened and found not to be EIA development (or is exempted). Ask the council whether your scheme needs screening.
Wales
Same structure as England, smaller size limit
Wales still uses the 1995 order, amended for Wales. Class A (5 ha or more) and Class B (0.4 to 5 ha) work the same way as in England, with the same 400 m rule, prior approval with 28 days and a site notice, 12 m height and 25 m road limits.
The main difference for a store: the ground area limit is 465 m² for both "any works or structure (other than a fence) for accommodating livestock or any plant or machinery arising from engineering operations" and any building.
Scotland
Class 18: agricultural buildings and operations
Covers buildings, private ways and "any excavation or engineering operations, requisite for the purposes of agriculture within that unit". Not on agricultural land less than 0.4 ha, and not for erecting a building within a historic battlefield.
Limits relevant to a store: works or structures for livestock or plant or machinery from engineering operations no more than 465 m²; buildings no more than 465 m² in a designated area and 1,000 m² elsewhere; height 12 m (3 m within 3 km of an aerodrome); not within 25 m of a trunk or classified road; and the 400 m rule for slurry, sewage sludge and housing pigs, poultry, rabbits or fur animals.
Prior approval applies to erecting a building or a significant extension or alteration of one, and to forming or altering a private way, with the same 28-day timetable.
Northern Ireland
Part 7 Class A: agricultural buildings and operations
Covers "works for the erection, extension or alteration of a building" and "any excavation or engineering operation; reasonably necessary for the purposes of agriculture within that unit". It does not apply if any of these is true:
- the land is less than 0.5 ha;
- "the building or structure to be erected is the first agricultural building on the unit";
- its nearest part "is more than 75 metres from the nearest part of a group of principal farm buildings";
- its nearest part "is less than 75 metres from a dwellinghouse (other than a dwellinghouse of any person engaged in agricultural operations on that unit)";
- the ground area exceeds 500 m² — counted together with other buildings and works provided in the past two years within 75 m;
- it is over 12 m high (3 m within 3 km of an airport);
- it is within 24 m of a special road, within 24 m of the middle of a trunk, first- or second-class road, or 9 m from the middle of other roads.
Part 7 has no separate 400 m rule for slurry and no prior approval step. If a store fails any condition, it needs a planning application.
Before you build: what to check
- Measure to the nearest non-farm building people use. England, Wales, Scotland: is the store within 400 m of its curtilage? Northern Ireland: is it within 75 m of a house that isn't someone's on your farm?
- Check your farm size and the parcel size against your nation's minimum.
- Work out the ground area against your nation's limit, including anything else built nearby recently where the order counts it.
- Check distance from roads and height.
- Check designations — designated or protected land, scheduled monuments, historic battlefields in Scotland — which change or remove the rights.
- Ask the council how it will treat your store type, and whether it needs prior approval, a full application or an EIA screening.
- Tell the environmental regulator — separately, and in time. See storage rules by nation.
- Grants: if a grant is involved, check its own rules on planning before you apply — see grants.
Questions
Does a slurry bag or a steel tank need planning?
The planning orders don't name store types. Whether permitted development covers a store depends on the conditions above — distance from houses, size, height, roads, farm size — and on how the council classes it. Ask the council.
My neighbour is a farmer. Does their house count for the 400 m rule?
Not if it is "a dwelling or other building on another agricultural unit which is used for or in connection with agriculture" — the order excludes those. A house that is no longer part of a farm would count.
How long does prior approval take?
The council has 28 days from receiving your application to tell you whether prior approval is needed. If it says nothing in that time, you can go ahead in line with what you submitted. If it says approval is needed, you wait for its decision.
Got a question this page didn't answer?
Ask us — you don't need to give your name, and every message is read by a person. Spotted something out of date? Tell us that too and we'll check and fix it.
A plain-English summary, not the law and not planning advice. Permitted development is a legal test and your council decides whether a project meets it. Always ask the council before you build.
Sources: Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2 Part 6 (Classes A and B, and paragraph D.1 definitions) and article 3(10); Town and Country Planning (General Permitted Development) Order 1995, Schedule 2 Part 6 (as amended in Wales); Town and Country Planning (General Permitted Development) (Scotland) Order 1992, Schedule 1 Part 6, Class 18; Planning (General Permitted Development) Order (Northern Ireland) 2015, Schedule Part 7. All read on legislation.gov.uk on 2 November 2026, which showed no outstanding changes for these parts. For the regulator notice, see the sources on storage rules by nation. Last reviewed 2 November 2026.